If the owner files a notice of completion, how many days does a contractor have to file a notice of lien from that date?

30 days

40 days

The answer is significant because, in Nevada, when an owner files a notice of completion, it triggers a specific time frame for contractors to protect their lien rights. A contractor has 40 days from the date that the notice of completion is filed to file a notice of lien. This timeframe is crucial for contractors to understand, as failing to file within this period can result in losing the right to claim a lien on the property for unpaid work.

Understanding this deadline is essential for contractors to ensure their ability to pursue payment through lien enforcement. Timely action is necessary to secure their legal rights in accordance with Nevada law. The other options represent incorrect durations, as they do not align with the established legal timeframe specified by state statutes. Knowing the correct timeline allows contractors to act promptly and protect their interests effectively.

Get further explanation with Examzify DeepDiveBeta

60 days

90 days

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy